Moragolla Hydropower

Moragolla Hydropower

The Feasibility study and Preparation of Detailed Design and Bidding Documents for construction of hydropower plant with 26.5MW installed capacity
and 85 GWh annual electrical energy generation is in progress.

The total estimated cost of the project is USD 6.35 Million and financial assistance is provided by Asian Development Bank under Sustainable Power
Sector Support II Project. The project is commenced on 24 September 2012 and completed 80% of Reviewing the Feasibility Study and will be completed
by 24 January 2014.
The ADB has agreed to fund the construction of this project under ADB loan of 2014.