Moragolla Hydro Power Project (31 MW)

Moragolla Hydro Power Project (31 MW)

Moragolla power project which constructed on the Mahaweli River Basin is located in the Ulapane area in Kandy District. It is expected to generate 100 GWh of energy annually. The ADB has provided a loan of $ 113.86 million for the project under the “Green Power Development and Energy Improvement Investment Programme” in 2017. Preliminary work of the project was commenced in 2018. The current physical progress of the project is 27%. Construction progress is slowed down due to COVID 19 pandemic situation in the country. It is expected to complete the project and commissioned by November 2023.